Short answer
- New LESCO solar connections no longer get net metering. Since 9 February 2026 every new application, and every capacity increase, is processed as net billing through the PITC Net Billing Portal.
- You must be a three-phase consumer, and your system cannot be bigger than your sanctioned load.
- For systems of 25 kW or below, LESCO approves the application itself. There is no NEPRA fee and no NEPRA approval step.
- On paper the steps add up to roughly two to three months of working days. In practice, missing documents and transformer limits are what slow people down.
This guide walks through the LESCO application in the order it actually happens, with the deadlines NEPRA’s rules give LESCO at each step. It is written for homeowners and factory owners in Lahore, Kasur, Sheikhupura, Okara and Nankana Sahib, the districts LESCO supplies.
Net metering or net billing: which one you are applying for
Most people still search for “LESCO net metering”, and most installers still call it that. The legal reality changed on 9 February 2026, when NEPRA notified the Prosumer Regulations 2026 (SRO 251(I)/2026) and repealed the 2015 net metering rules.
LESCO has confirmed how it applies this. According to Business Recorder (24 June 2026), applications submitted after 9 February are processed through the PITC Net Billing Portal, and upgrades or capacity increases on existing net metering connections also fall under net billing. The same report put LESCO’s net metering base at 135,837 connections and 2,053 MW by May 2026, which is why some transformers in Lahore are already near their solar limit.
Under net billing, every unit you import is charged at your normal tariff, and every unit you export is credited at NEPRA’s national average energy purchase price, reported at about Rs8 to Rs11 per unit. We explain the money side in detail in our guide to net billing in Pakistan and what NEPRA’s 2026 rules mean for your bill. This article sticks to the paperwork.
Check these four things before you apply
Most rejected or stalled applications fail on one of these. Check them before you buy panels, not after.
1. Your connection must be three-phase
The regulations define an applicant as a three-phase 400V or 11kV consumer. If your house is on a single-phase connection, you need a three-phase conversion from LESCO first. That is a separate application with its own demand notice, so start it early.
2. System size cannot exceed your sanctioned load
Regulation 3(2) caps the solar system at the sanctioned load printed on your bill. A house sanctioned at 7 kW cannot connect a 10 kW system. If you need more, apply for a load extension before the net billing application. Under net billing, sizing much above your daytime use rarely pays anyway.
3. Your transformer must have room
LESCO is not allowed to accept an application once solar on your distribution transformer reaches 80% of its rated capacity. In heavily solarised blocks this is the single biggest risk. Your SDO office can tell you where your transformer stands; ask before you commit.
4. Your inverter must meet the standard
Grid-connected inverters must comply with UL 1741, which covers anti-islanding (the inverter must shut off when the grid goes down, so linemen are not hurt). You also need a manual disconnect switch with a visible break. Ask for the inverter’s certificate before you buy.
Large systems: at 250 kW and above, NEPRA’s rules also require a load flow study, done through LESCO or a consultant registered with the Pakistan Engineering Council. Factories should budget time for this.
Documents and information you will need
The standard application form in the regulations (Schedule II) asks for the details below. LESCO or the portal may ask for more, so treat this as the minimum, not the full list.
- Applicant’s name, CNIC copy (or company registration number), address, phone and email
- A recent LESCO bill with your reference number and sanctioned load
- Location of the system and your expected yearly consumption and solar production
- A single-line diagram of the system
- Inverter make, model, serial number and AC rating, plus its datasheet and certificate
- Solar panel make, model and quantity, with datasheets
- Name, phone and address of the installing firm, and the installer’s signature on the form
Keep the signed copies. The date of your agreement decides which rules apply to you for its five-year term.

The LESCO application, step by step
These are the steps and deadlines set in regulations 3 and 4 of the Prosumer Regulations and the standard interconnection agreement. All days are working days.
| Step | Who acts | Deadline in the rules |
|---|---|---|
| LESCO gives you the forms and information on request, free | LESCO | 2 days |
| Acknowledge application, say if anything is missing | LESCO | 5 days |
| Supply any missing documents | You | 3 days |
| Initial technical review | LESCO | 15 days |
| Sign the interconnection agreement | Both | 7 days |
| Connection charge estimate (demand notice) issued | LESCO | 7 days |
| Pay the demand notice | You | 7 days |
| Install and commission meter and interconnection | LESCO | 15 days after payment |
| NEPRA concurrence (above 25 kW only) | NEPRA | 7 days after documents |
1. Submit the application on the PITC portal
New applications now go online rather than as paper files at the division office. When the application is submitted, the portal gives a registration number and receiving date, as reported when DISCOs moved to the portal. Save that number; every follow-up depends on it. Most homeowners have their installer file the application, but it is your connection and your agreement, so keep your own copy of everything.
2. Document check and technical review
LESCO has five working days to tell you whether the file is complete, and you have three to fix gaps. The 15-day technical review is where transformer capacity and your sanctioned load are checked. If the system is not feasible, LESCO must return the application with reasons within three days.
3. Agreement, demand notice and payment
Once the review passes, you and LESCO sign the Distributed Generation Interconnection Agreement. It runs for five years from commissioning and can be renewed for further five-year terms by mutual consent. LESCO then issues the connection charge estimate, which you pay within seven working days.
4. Testing, meter and commissioning
Under the agreement, you notify LESCO in writing when the installation is finished, at least 15 working days before connecting to the grid. LESCO may test the system (within ten working days) against the Ministry of Energy’s installation SOPs, then installs the bidirectional meter (or two separate meters) and commissions the connection. Do not export to the grid before this.
5. Approval: LESCO for small systems, NEPRA for large
When the 2026 rules first came in, every system needed NEPRA “concurrence” and a fee of Rs1,000 per kW. That has been rolled back twice. In April, NEPRA removed the fee and licence for systems of 25 kW or below, backdated to 9 February. In August it amended the rules again so that systems of 25 kW or below need no NEPRA concurrence at all; the DISCO approves them.
Above 25 kW, LESCO forwards the signed agreement to NEPRA with proof of the Rs1,000 per kW fee and an affidavit on Rs50 stamp paper. NEPRA is meant to decide within seven working days. Billing under the agreement starts only after that concurrence, and it lapses if the system is not running within six months.
Want the paperwork handled properly?
PEMCO offers net billing application support with every solar system we install. WhatsApp a photo of your LESCO bill and we will check your phase, sanctioned load and the right system size before you spend anything.
What it costs
| Cost item | 25 kW or below | Above 25 kW |
|---|---|---|
| NEPRA fee | Nil | Rs1,000 per kW, one time |
| Bidirectional meter (or two meters) | You pay | You pay |
| Interconnection work up to the connection point | You pay | You pay |
| Grid upgrades needed only for your system | You pay | You pay |
| Affidavit on stamp paper | Not needed for NEPRA | Rs50 stamp paper |
The meter and interconnection amounts come on LESCO’s demand notice, so we do not quote a fixed figure here: it depends on single or dual metering and the work at your premises. If LESCO has no meters in stock, the rules let you buy one yourself, but it must be tested by LESCO before installation. A 50 kW factory system, for example, pays Rs50,000 to NEPRA on top of the meter.
Why applications get stuck
The deadlines above are what the rules say, not a promise. From what Lahore homeowners report, the delays usually come from a handful of causes:
- Single-phase connection discovered after the panels are already on the roof.
- System larger than sanctioned load, so the file goes back for a load extension.
- Transformer at its 80% solar limit; nothing moves until LESCO upgrades it.
- Single-line diagram that does not match the installation, which fails at testing.
- Inverter without a valid certificate, or settings that do not match the datasheet.
The honest advice: get the three-phase connection, sanctioned load and transformer question settled first, then buy equipment. If your transformer is full, a hybrid or off-grid design that uses its own power without exporting may be the practical route while you wait. Our comparison of lithium-ion and lead-acid batteries for solar helps if you go that way.
Watch out for agents. The Power Division has said publicly that consumers do not need to pay any individual to speed up their application. Fees go to LESCO or NEPRA through official channels only.
Applied before 9 February 2026?
LESCO moved 1,204 net metering applications that were pending on 9 February onto the PITC portal. Nationally, the Power Division said in September that 11,695 of 16,654 pending cases had been cleared, and that PITC is contacting those consumers directly by SMS and WhatsApp. You can check the status at nmverification.pitc.com.pk, according to ARY News.
If you already have a signed net metering agreement from before 9 February, you keep its terms until it expires. Our older guide to how net metering works covers that system.

Frequently asked questions
Can I still get net metering from LESCO?
Not for a new connection. Applications made after 9 February 2026, including upgrades and capacity increases on existing connections, are processed as net billing through the PITC portal. Existing agreements signed before that date keep their terms until they expire.
How long does LESCO take to approve net billing?
The deadlines in NEPRA’s regulations add up to roughly two to three months of working days from application to commissioning. Missing documents, a single-phase connection, an oversized system or a full transformer can add much more.
Do I need NEPRA approval for a 10 kW home system?
No. Since NEPRA’s August 2026 amendment, systems of 25 kW or below need no NEPRA concurrence and pay no NEPRA fee. LESCO approves them directly.
Can I apply with a single-phase connection?
No. The regulations only accept three-phase 400V or 11kV consumers, so a single-phase house must convert to three-phase with LESCO first.
Can I install more solar than my sanctioned load?
No. The system cannot exceed your sanctioned load. Apply for a load extension first if you need a bigger system.
Get your system and application right first time
PEMCO Engineering designs on-grid, hybrid and off-grid solar for homes, commercial buildings and factories across Lahore and Punjab, with net billing application support. See our solar system installation service. Call or WhatsApp 0322 4773987, or use the contact form for a free consultation. Free site survey in Lahore and nearby areas.
Written by the PEMCO Engineering Team. Rules checked against NEPRA’s Prosumer Regulations 2026 and news reports on 17 November 2026. This is general information, not legal advice; LESCO’s portal and forms can change, so confirm current requirements with LESCO before you apply.