Adding a Lift to an Existing House in Pakistan: Shaft, Structure and Approvals

  • Post published:

By the PEMCO Engineering Team, Lahore. Updated 18 November 2026.

Short answer

  • Most existing Pakistani houses can take a lift. The real questions are where the shaft goes and how much structure has to be cut.
  • A modern RCC frame house (columns and beams) is far easier than an old load-bearing brick house, where almost every wall carries weight.
  • Cutting a floor slab is a structural change. It needs a structural engineer’s design and, in DHA Lahore or LDA areas, approved revised drawings before work starts.
  • If you can’t cut slabs, a self-supporting platform or screw-drive lift or a lift tower built against an outside wall is often the cleaner route.

Families usually start thinking about a lift after the house is finished: a parent’s knees give out, someone comes home after surgery, or the top floor is simply too far. This guide is for that situation. It covers what an engineer looks at first, where a shaft can realistically go, what the rules in Lahore say, and the order of work so nothing has to be broken twice.

What an engineer checks first

Before anyone talks about cabins and finishes, four things decide whether a retrofit is easy, hard or a bad idea.

1. How the house is built

Most houses built in Lahore over the last twenty years have an RCC frame: concrete columns and beams, with brick walls filling the gaps. In these houses you can usually open a slab panel between beams without touching a column. Older houses, and many smaller ones, are built with 9-inch load-bearing brick walls, where the walls themselves hold up the roof. There, every opening needs more careful design, and sometimes new steel or concrete members.

Your original structural drawings help enormously. If you don’t have them, the engineer will have to locate beams and reinforcement on site, which takes longer.

2. A clear vertical line

A lift needs the same footprint stacked on every floor it serves. A cupboard on the ground floor is no use if the room above has a bathroom with drain pipes in that exact spot. Plumbing stacks, electrical risers and beams running through the space are the usual surprises.

3. Pit and headroom

A conventional lift needs a pit below the lowest floor and extra height above the top stop. Digging a pit inside a finished ground floor means breaking tiles, possibly a plinth beam, and dealing with damp. Low-pit home lifts reduce this a lot; our guide to a lift for home in Pakistan lists typical footprint, pit and headroom figures by lift type.

4. Electricity supply

Many compact home lifts run on single-phase power; larger traction lifts usually need three-phase. If your house is single-phase, check the model before you buy, because a phase change from your DISCO is a separate application that takes time.

Send us these four things first: photos of the staircase and the spot you have in mind on every floor, your structural drawings if you have them, a recent electricity bill, and how many floors you want to serve. That is enough for a first opinion.

Where the shaft can go

In existing Pakistani houses, a lift almost always ends up in one of four places. Each has a different amount of breaking.

LocationStructural workGood forWatch out for
Stairwell void (the open well between flights)Often none or little: the void already passes through every floorSmall platform, screw-drive or tube liftsThe void must be wide enough; the stair must stay legal and usable
Stacked rooms or cupboardsSlab openings on each floor, new edge beamsCompact traction or platform liftsPlumbing and wiring in the same line
Lift tower against an outside wallNew foundation and shaft outside; openings in the wall at each landingHouses with no space insideClear spaces under bylaws; waterproofing at the joint
Courtyard or lightwellNew shaft in an open spaceOlder houses with an internal courtyardLoss of light and ventilation to rooms around it
Which option fits depends on your plot, structure and the bylaws for your area.

The outside tower option deserves a warning. DHA Lahore’s regulations set compulsory clear spaces on every side of a house (for example 5 feet front and 3 feet on the sides for a 5 marla plot), and no construction is allowed in them. A tower that eats into a clear space will not be approved. Check your plot’s setbacks before you fall in love with that idea.

Compact lift with stainless steel doors fitted into a small footprint
Illustration: compact lifts need roughly the space of a large wardrobe on each floor.

Cutting a slab: what really happens

Cutting a hole in a floor slab is a structural decision, not a demolition job. The slab you remove was carrying load and passing it to the beams around it. Once it is gone, that load has to find a new path.

The usual method in an RCC house is to frame the opening with new edge beams (trimmer beams) tied into the existing beams, so the cut edges are supported again. The structural engineer designs these, decides where the cut can and cannot go, and specifies temporary props during the work. In a load-bearing brick house the engineer may need steel sections or new columns as well.

  • Locate the steel first. The cut should be planned after finding the beams and main reinforcement, not by guesswork with a hammer drill.
  • Prop before cutting. Temporary supports go in below the slab before any concrete is removed.
  • Cut, don’t hammer. Wall saws and core drills give clean edges and far less vibration and cracking than breaking with a chisel.
  • Protect the house. Dust sheets, sealed doors and a plan for moving debris out. The family will usually keep living there.
  • Waterproof the roof opening. If the shaft goes through the top slab to a machine room or overrun, that joint must be detailed properly before the monsoon.

This is also why we push families building new houses to leave a framed, future lift opening in the drawings. It costs very little at the design stage and saves most of the work above.

Which lift type suits a retrofit

The less the lift leans on the building, the easier the retrofit. Here is how the main types compare for an existing house.

Self-supporting platform or screw-drive lifts

These come with their own shaft frame that stands on the floor and needs little or no pit, so the walls don’t carry the lift. Aritco, one maker of this type, says most of its home lifts are installed in at most four days once the openings are ready. They are slower than a passenger lift and carry fewer people, which is fine in a house.

Compact traction lifts (MRL or with machine room)

Faster and roomier, but they need a proper shaft, a pit and a guide rail system fixed to the structure. In a retrofit this means more civil work. A machine-room-less (MRL) design avoids building a room on the roof, but in DHA Lahore an MRL layout must be discussed with and approved by the authority before installation.

Hydraulic lifts

Good for two or three stops and heavy loads, and they place much of the load into the pit floor rather than the top of the building. You need space near the shaft for the pump unit.

Vacuum tube lifts

No pit and no machine room, and the tube is the structure, so they are among the easiest to retrofit. The trade-off is a small cabin, often a tight fit for a wheelchair, and a high price per person carried.

Not sure your house can take a lift?

WhatsApp us photos of your stairwell and floors, plus your drawings if you have them. Our engineers will tell you which location and lift type make sense. Free site survey in Lahore and nearby areas, video consultation anywhere in Punjab.

Approvals in DHA Lahore and LDA areas

Adding a lift to a built house counts as an addition or alteration to the structure, so in controlled housing areas it needs approval before work starts. Skipping this tends to surface later, when you apply for a completion certificate or try to sell.

DHA Lahore

DHA Lahore’s Construction & Development Regulations (April 2026 edition) are direct about this:

  • Regulation 20: revised drawings must be approved before any addition or alteration to the structure of the building.
  • Regulation 14: drawing submissions include structural drawings and a structure stability certificate.
  • Regulation 33: a lift machine room on a house can be at most 75 sq ft, with a maximum height of 45 feet from the crown of the road, while the rest of the stair mumtee stays within 39 feet.
  • Annex-E: elevators in houses and commercial buildings must pass a mandatory inspection checklist, including the emergency landing device, speed governor, pit buffers, door sensors, intercom, a maintenance log book and a preventive maintenance contract.

DHA’s separate guidelines for lift installation list what is mandatory for houses: a stability certificate, backup power (ELD/UPS), door interlocks, earthing, a single line diagram, an alarm, cabin light and fan, and a maintenance contract. DHA notes that missing items cause trouble later at inspection and when issuing completion certificates. Plazas have a longer mandatory list; our guide to passenger lifts for plazas and apartments in Lahore covers it.

LDA and other Punjab authorities

The LDA Building and Zoning Regulations define an “Addition & Alteration Plan” as plans submitted for approval of any structural change made after a building is completed. Gujranwala and Rawalpindi development authorities adopted the LDA regulations with local changes, so the same principle applies there. Private societies such as Bahria Town have their own building control offices. Ask your society or authority which forms apply before you cut anything.

Practical tip: get the structural engineer, the architect and the lift supplier to agree on one drawing set before you submit. Approvals are much slower when the shaft size on the plan doesn’t match the lift you actually buy.

Step-by-step: survey to handover

1. Survey and feasibility

Measure every floor, find beams and services, check the electricity supply, and shortlist one or two locations and lift types.

2. Choose the lift model

Fix the exact model before structural design, because shaft size, pit depth, headroom, door sizes and fixing loads all come from the manufacturer’s drawing.

3. Structural design and drawings

The structural engineer designs the openings, edge beams, pit and any machine room, and issues the stability certificate. The architect updates the plans.

4. Approval

Submit revised drawings to DHA, LDA or your society and wait for approval. Apply for a phase change at the same time if the lift needs three-phase power.

5. Civil work

Props, cutting, edge beams, pit, shaft walls or frame, landing openings and waterproofing. Let new concrete cure properly before the lift team fixes rails to it.

6. Lift installation and wiring

Rails, cabin, drive, controller, landing doors and call buttons on every floor, a dedicated circuit with its own breaker, earthing and the ELD/ARD backup.

7. Testing, inspection and handover

Load and safety tests, a power-cut rescue test, then authority inspection where required. At handover you should receive the emergency door key, the single line diagram, manuals, and a signed maintenance contract with a log book.

Inside a lift cabin: stainless steel doors, button panel, floor display and ceiling light
Illustration: alarm button, light, fan and emergency instructions are part of DHA’s house checklist. Photo: meowbuild, WordPress Photo Directory (CC0).

When a retrofit is the wrong call

We would rather tell you no than force a lift into a house that can’t take it safely:

  • The only possible location needs a column or main beam removed. That is a major redesign, not a lift job.
  • The slab is weak, cracked or badly built. Fix the structure first, or choose a self-supporting lift that doesn’t load it.
  • The shaft would take a required staircase below a safe width, or block the only exit from upper floors.
  • One person needs to go up one flight. A stairlift on a straight staircase may solve it with no structural work at all.
  • You may sell soon. A large retrofit may not pay back in the sale price. Our home lift price guide shows what the lift and the civil work typically cost.

If you are still comparing models, our guide on how to choose a home elevator in Pakistan covers safety features and what to check at handover. For Islamabad houses, see lift installation in Islamabad, which covers the DHA Islamabad lift-well height rules.

Frequently asked questions

Can I install a lift in a house that is already built?

Usually yes. RCC frame houses can normally take a slab opening between beams with new edge beams designed by a structural engineer. Old load-bearing brick houses need more careful design. Where cutting slabs is difficult, a self-supporting platform lift in the stairwell or a lift tower against an outside wall are common alternatives.

Do I need DHA approval to add a lift to my house?

Yes, if it involves structural changes. DHA Lahore’s regulations require approved revised drawings before any addition or alteration to a building’s structure, with a structural stability certificate, and lifts must pass DHA’s mandatory inspection checklist. A machine-room-less design needs DHA’s prior approval.

Is it safe to cut the floor slab for a lift?

It is safe when a structural engineer designs the opening, the slab is propped before cutting, the concrete is cut with saws rather than broken, and new edge beams are added to carry the load around the hole. It is not safe to cut by guesswork.

Which lift is easiest to fit in an existing house?

Self-supporting lifts that need little or no pit, such as platform or screw-drive home lifts and vacuum tube lifts, need the least structural work. Traction lifts need a full shaft, pit and fixings into the structure, which means more civil work in a finished house.

Will my single-phase connection be enough?

For many compact home lifts it is, but larger traction lifts usually need three-phase power. Check the exact model’s supply requirement, and if you need three-phase, apply to your DISCO early because it is a separate process.

Talk to an engineer about your house

PEMCO Engineering has installed home lifts, passenger lifts and cargo lifts in houses, commercial buildings and factories across Punjab. See our elevator and lift installation service. Call or WhatsApp 0322 4773987, or use the contact form for a free consultation.

Written by the PEMCO Engineering Team. Rules checked against DHA Lahore’s Construction & Development Regulations (April 2026 edition), DHA Lahore’s lift installation guidelines and the LDA Building and Zoning Regulations on 18 November 2026. This is general guidance; structural work must be designed by a registered structural engineer for your specific house.